午夜男女视频一区二区|国产AV无码麻豆|国产精品一V二V在线观看|欧美精品一二三区

    
    
        1. FBE/2FBE Pipe External Coating Production Line

          new time:2015/3/7 10:06:02


           

          FBE/2FBE Pipe External Coating Production Line

           

          Note:1、Pipe incoming rack  2、Spiral conveyor for blasting line  3、Gas preheating furnace  4、Pipe external blasting machine  5、Blasted pipe outgoing rack  6、Pipe internal blowing device  7、Inspection platform  8、Linear conveyor for waste pipe return  9、Waste pipe return rack  10、Spiral conveyor for coating line  11、IF heating device  12、FBE spraying device  13、Cooling tower device  15、Pipe coating cooling room  16、Coated pipe outgoing rack  17、End-of-pipe treatment device  18、Finished pipe outgoing rack

           

           

          Technical Parameter

          S.N.

          Name

          Technical parameters

          1

          Pipe diameter

          Φ101~Φ1219mm

          2

          Pipe length

          8~12.5m

          3

          Voltage、frequency

          380v/220v、50HZ

          4

          Total power

          About 4300KW

          5

          Air pressure

          0.4~0.6Mpa

          6

          The compressor pressure/throughput

          0.8Mpa/10X2m3

          7

          Water consumption

          2% of the total water amount

          8

          Productivity

          300-400m2/hr

           

          contact

          Langfang Dingsheng Mechanical Equipment Co., Ltd

          Tel:86-0316-2207771

          86-0316-2207773

          Tel:18831688900

          Fax:86-0316-2231218

          E-mail:dshjx@vip.sina.com

          Add:NO. 198, AI'MIN ST. EAST, LANGFANG,HEBEI, CHINA